01/11/2022
Missouri State Auditor Nicole Galloway
today released an audit of the city of Town and Country, located in St. Louis
County. Residents of Town and Country requested the audit through the petition
process.
Auditors detailed poor planning by the city
on the Town Square development project, resulting in changes that cost
taxpayers more than $1.3 million beyond than the original cost estimate.
Additionally, the Board of Aldermen approved significant changes to the project
without competitively bidding the work. Examples include modifications to landscaping and trail
connections ($369,324); modifications to pavilion and structures ($627,399);
and supply and installation of security cameras ($50,290).
Additionally, auditors found that the Planning and Public Works
department did not ensure the city's contractor obtained the required county
permits for construction of the Mason Trail project prior to starting the
project. The city eventually ended the trail project and repaired the area
impacted by the initial work. The unnecessary costs to the city for all the
work totaled $140,313.
In their response to the audit, city officials agreed with
Auditor Galloway's recommendation that all project details be finalized before
entering into a contract for construction projects, and to ensure all required
permits are obtained prior to starting construction.
"This audit has revealed several
shortcomings of the Town Square project that resulted in unnecessary added
costs for taxpayers," Auditor Galloway said. "I appreciate the
engagement of citizens in this process and the willingness of town officials to
adopt our recommendations in order to prevent similar mistakes in the
future."
Auditors also recommended improvements in
the city's procurement procedures and contracts, accounting controls and
procedures, compliance with the city code regarding alleged violations of the
code of ethics, closed meeting minutes documentation, and electronic
communication policies.
A complete copy of the audit, which gives a
rating of "good," is available here.