Name of City and/or County:
Strafford
Name of Plan or Project:
Strafford South West MO Regional Rail Park TIF
Report Period:
10/1/2020 to 9/1/2021
Name of the Person Who Prepared this Annual Report:
Laura Lashley
City or County Contact Agency:
Private Sector Developer:
South West Missouri Rail and Business Park, LLC
Original Date Plan/Project Approved:
Most Recent Plan Amendment:
School District:
Strafford School District
Originally consisted of four 4 parcels of real property located south of Interstate 44 in the city of Strafford, Greene County, Missouri. The area is bounded on the North by West Old Route 66 and on the West by State Route 125.
Description of Plan/Project:
To establish TIF development assistance in the district in order to facilitate redevelopment of the Area, to cure the economic underutilization of the Area, to alleviate those conditions that cause the Area to be a Blighted Area, and to further the objectives of the Citys Comprehensive Plan.
Plan/Project Status:
Starting-Up
How was the "but-for" Determination Made?:
A, B, C, and D all apply. As documented and described within the Plan, the Redevelopment Area meets the qualifications of a Blighte Area, as determined through completion of a blight qualification analysis which provided evidence that 100 of the parcel
Number of Relocated Residences During This Report Period:
0
Number of Relocated Businesses During This Report Period:
0
Number of Parcels Acquired Through Use of Eminent Domain Power During This Report Period:
0
Identify Any Businesses That Have Relocation to the Redevelopment Area During this Report Period:
Estimate of Retained Jobs:
0
TIF REVENUE DEPOSITS TO THE SPECIAL ALLOCATION FUND AS OF THE REPORT DATE:
Payments in Lieu of Taxes (PILOTs):
Total Received since inception:
$0.00
Amount on Hand: (As of Report Date)
$0.00
Economic Activity Taxes (EATs):
Total Received since inception:
$0.00
Amount on Hand: (As of Report Date)
$0.00
Total Revenue on hand in the Special Allocation Fund as of Report Date:
EXPENDITURES FOR TOTAL PROJECT COSTS FUNDED BY TIF:
Total Since Inception:
Report Period Only:
Public Infrastructure (streets, utilities, etc):
Site Development (grading, dirt moving, etc):
Rehab of Existing Buildings:
Acquisition of Land or Buildings:
AMOUNT PAID ON DEBT SERVICES:
Payments of principal and interest on outstanding bonded debt:
This Reporting Period:
$0.00
Reimbursement of developer for eligible cost:
This Reporting Period:
$0.00
Reimbursement to city/county (or other public entity) for eligible costs:
Since Inception:
$1,435.00
This Reporting Period:
$1,435.00
ANTICIPATED TIF REIMBURSEMENT COSTS:
Public Infrasture and Site Development Costs:
$0.00
Property Acquisition and Relocation Costs:
$0.00
Project Implementation Costs:
$0.00
Total Anticipated TIF Reimbursable Project Costs:
$13,697,871.00
ANTICIPATED TOTAL PROJECT COSTS:
$99,216,627.00
MATURITY OF TIF OBLIGATIONS:
Original Estimate (# of Years to Retirement):
23
Current Anticipated Estimate (# of Year to Retirement):
23
ESTIMATED INCREASE IN TAX GENERATION:
Original Assessed Value of the Redevelopment Project:
$10,240.00
Assessed Valuation Added to the Redevelopment Project:
$17,700.00
Anticipated Assessed Value at Time of District Termination:
$27,841,888.00
Total Amount of Base Year EATs:
$0.00
Total Amount of Base Year PILOTs:
$548.00
Total Annual EATs Anticipated at Time of District Termination:
$0.00
Total Annual PILOTs Anticipated at Time of District Termination:
$0.00
Percentage of EATs Captured:
50%
Total Years Anticipated to Capture EATs:
23
Percentage of PILOTs Captured:
100%
Total Years Anticipated to Capture PILOTs:
23